PROJECT PHOTOS

The following photos are in order with most recent on the top:
Abutment 1 for widening Route 5/15 NB at the Charter Oak Bridge (Bridge 6000) May 2020

Abutment 1 for widening Route 5/15 NB at the Charter Oak Bridge (Bridge 6000)


Concrete pour for Pier 1 footing for widening Route 5/15 NB at the Charter Oak Bridge (Bridge 6000) May 2020

Concrete pour for Pier 1 footing for widening Route 5/15 NB at the Charter Oak Bridge (Bridge 6000) May 2020

Concrete pour for Pier 1 footing for widening Route 5/15 NB at the Charter Oak Bridge (Bridge 6000) May 2020

Concrete pour for Pier 1 footing for widening Route 5/15 NB at the Charter Oak Bridge (Bridge 6000) May 2020

Pier 3 stem footing for widening Route 5/15 NB at the Charter Oak Bridge (Bridge 6000) May 2020

Facing north, construction site of future I-91 NB Exit 29

Facing north, abutment for future I-91 NB Exit 29 (Bridge 6947)

Facing north, Retaining Wall 103 and abutment for future I-91 NB Exit 29 (Bridge 6947)

Retaining Wall 103 construction, for future I-91 NB Exit 29 (Bridge 6947)

New abutments for widened I-91 NB bridge over Airport Road (Bridge 480) May 2020

New abutments and pier for widened I-91 NB bridge over on-ramp to I-91 SB and Route 5/15 SB from Airport Road (Bridge 1466) May 2020

Abutments & pier for widened I-91 NB bridge over Route 5/15 - (Bridge 813) May, 2020

Abutments & pier for widened I-91 NB bridge over Route 5/15 - (Bridge 813) May, 2020

Installing barrier under I-91 NB bridge over Route 5/15 (Bridge 813)

Installation of drainage in the median of I-91 in Wethersfield

Installation of drainage in the median of I-91 in Wethersfield, may 2020

Forming for abutment and piers for new Exit 29 bridge (Bridge 6947)

Forming for abutment and piers for new Exit 29 bridge
Soil nail wall in East Hartford along Route 5/15 NB for roadway widening - April 2020





Comparative Construction Photos

Widening of I-91 NB over Route 5/15


Widening of I-91 NB

Site of future I-91 NB Exit 29

Construction Photos March 2020

Charter Oak Bridge new Pier 3 concrete pour today - 3/31/2020

Nighttime bridge deck and wingwall demolition on I-91 NB over Airport Road on-ramp - 3/26/2020


Nighttime bridge deck and wingwall demolition on I-91 NB over Airport Road on-ramp - 3-26-2020

Route 15 NB and Exit 89 prior to new traffic shift

Click for more information on the Route 5/15 NB Exit 89 traffic shift
Route 5/15 NB Exit 89 off-ramp; site of upcoming traffic shift to happen week of 3/30/2020

New pier for widened I-91 NB Bridge over Route 5/15 - March 20, 2020

Slopes widened for roadway widening - March 20, 2020

Route 5/15 NB new Exit 89, ready for paving - March 20, 2020

New pier for widened portion of Charter Oak Bridge (pier 2)

Site for new pier for the widened portion of Charter Oak Bridge (pier 1

Soil nail wall in East Hartford along Route 5/15 NB for roadway widening - March 20, 2020

Soil nail wall in East Hartford along Route 5/15 NB for roadway widening - Feb. 2020

Steel repairs on the Charter Oak Bridge, March 2020

5/15 NB with casing installation for widening. Note the parapet has been removed.

5/15 NB Parapet Demolition

Steel casings for steel piles for widening of I-91 at Charter Oak Bridge

I-91 Bridge over Route 5/15 - pier 1 concrete pour for widening of I-91

New I-91 Exit 29 pier and abutment taking shape

Footing for widened I-91 at Charter Oak Bridge


Facing north, Route 5/15 NB Traffic split before Exit 87 - January 2020


Facing southeast, Route 5/15 with traffic split and I-91 bridge demolition - January 2020
Charter Oak Bridge deck reconstruction - January 2020

Pumping concrete into abutment #1 for new I-91 NB Exit 29

Sound barrier wall removal in East Hartford
Pile driving for roadway widening - September 2019
Paving I-91 at night - July 2019