Week March 1, 2021
The new I-91 NB Exit 29 Bridge seen from I-91 SB ground level.
- Completing parapets and bridge joints on new Exit 29 bridge (bridge 6947)
- Completing bridge joints on Charter Oak Bridge (bridge 6000)
- Constructing Walls 104A and 104B on new Exit 29 alignment
- Constructing new approach roadway for new Exit 29 alignment (I-91 median/Wall 103/Bridge 6947 Abutment 1)
- Continue steel repairs on Charter Oak bridge
- Continue widening of Bridge 813 (I-91 over Route 15)
- Continue widening of Bridge 1466 (I-91 over Airport Road on ramp to I-91 SB)
- Continue widening of Bridge 480 (I-91 over Airport Road)
- Continue lowering of Route 15 roadway under I-91 (Bridge 813)
- Continue reconstruction of Route 15 median under I-91 NB bridge
- Continue reconstruction of I-91 median in Wethersfield
- Continue widening of Route 15 NB bridge over Main Street in East Hartford
- Continue widening of Route 15 NB bridge over Silver Lane in East Hartford
- Continue installation of new sign foundations
- Continue installation of new highway lighting throughout project
Daytime Closures
No Daytime Lane Closures are anticipated this week through Sunday, 3/7.
Nighttime Closures
Nighttime Lane Closures are anticipated this week through Sunday, 3/7.
Nighttime Road Closures with Detours
Nighttime Road Closures and Detours are anticipated this week through Sunday, 3/7.
Long-term Road Closure and Detours