ROAD/LANE CLOSURES
Nighttime Lane Closures possible Tuesday through Friday nights, 7/5 through 7/8 between the hours of 8:00 PM and 6:00 AM, weather permitting:
  • I-91 NB (Great Meadow Road to Exit 27) for final paving
  • I-91 SB (Whitehead Highway to on-ramp from Route 3 NB 26) for drainage work 
  • Route 5/15 NB (Exit 85 to Exit 89) for milling and paving 

Nighttime Road Closures  
Nighttime Road Closures and Detours are possible between the hours of 8:00 PM and 6:00 AM, weather permitting, as follows: 

No closures are anticipated Saturday, 7/9.

LONG-TERM ROADWAY CLOSURES AND DETOURS


What's Happening Now

  • Completing bridge joints on Charter Oak Bridge (bridge 6000)
  • Continue Route 15 median work in East Hartford
  • Continue reconstruction of Route 15 SB Exit 86 gore
  • Continue ramp milling and paving project wide
  • Continue installation of new highway lighting throughout project
  • Continue work for the improvement of I-91 southbound (SB) in Wethersfield
  • Continue grading slopes, installing new landscaping and turf establishment
  • Installing new metal beam rail and curb
  • Continue shim paving of I-91 NB in Wethersfield