Update for Week of 5/22/2022

Posted on May 20, 2022

ROAD/LANE/SHOULDER CLOSURES
Nighttime Lane Closures
Nighttime Lane Closures possible Sunday through Thursday nights, 5/22 through 5/26 between the hours of 8:00 PM and 6:00 AM, weather permitting:
  • I-91 NB (Exit 24 to Exit 29) for overhead sign removal, shim paving, and to pave the median 
  • I-91 SB (Whitehead Highway to Exit 28) for curbing
  • I-91 SB (Cove Bridge to Route 3 NB on-ramp to I-91 SB) for overhead sign removal and shim paving
  • Route 5/15 NB (Exit 89 to Exit 91) to pave the median 
  • Route 5/15 SB (I-84 WB Exit 57 ramp to the Charter Oak Bridge) to pave the median
  • I-84 WB (Exit 57 ramp to Route 5/15SB) to pave the median
 
Intermittent Highway Closures
  • Close I-91 NB and SB - Intermittent 15-minute Highway Closures Sunday night, 5/22, from 12:00 AM to 5:00 AM, for overhead sign removal and shim paving.
 
Nighttime Road Closures  
Nighttime Road Closures and Detours are possible between the hours of 8:00 PM and 6:00 AM, weather permitting, as follows: 


No closures are anticipated Friday through Monday, 5/27 through 5/30.

LONG-TERM ROADWAY CLOSURES AND DETOURS


What's Happening Now

  • Completing bridge joints on Charter Oak Bridge (bridge 6000)
  • Continue Route 15 median work in East Hartford
  • Continue reconstruction of Route 15 SB Exit 86 gore
  • Continue ramp milling and paving project wide
  • Continue installation of new highway lighting throughout project
  • Continue work for the improvement of I-91 southbound (SB) in Wethersfield
  • Continue grading slopes, installing new landscaping and turf establishment
  • Installing new metal beam rail and curb
  • Continue shim paving of I-91 NB in Wethersfield