Click on the blue links below to see photos of, or announcements about, the work.
 

Daytime Lane Closures

No Daytime Lane Closures are anticipated this week

Nighttime Lane Closures

Nighttime Lane Closures possible between the hours of 8:00 PM and 6:00 AM, Tuesday through Friday nights, weather permitting:
  • I-91 NB (Exit 27 to Exit 29) for bridge work
  • I-91 SB (Whitehead Highway to Exit 26) – to seal and pave concrete patches
  • I-91 SB (On-ramp from Route 5/15 NB to Exit 26) for patching on Great Meadow Road Bridge
  • I-91 SB (Exit 28 to Exit 26) to mill for new concrete patches and Great Meadow Road Bridge patching
  • Route 5/15 NB (Exit 86 to Exit 89) for bridge demolition
  • Route 5/15 NB (Exit 89 ramp) for bridge demolition and structural steel work

Nighttime Road Closures with Detours

Nighttime Road Closures possible between the hours of 8:00 PM and 6:00 AM, as follows:

 No closures are anticipated Saturday and Sunday 5/30 and 5/31.